Fall 2001-Fall 2005 Planning Period
Academic Facilities
PLANNED NEW CONSTRUCTION
Site District Project NASF GSF Cost* Potential
Fund Source
N1 NE Kim Engineering Building 79,200 141,300 $50,000 State
N2 NE Chemistry Teaching Building 32,755 58,500 $30,200 State
N3 NE Computer Science Instructional Center 21,000 37,222 $10,300 System
N4 N Research Greenhouse Complex 46,655 65,500 $17,500 State
N5 SW Van Munching Hall Addition 56,601 103,000 $24,800 State, Institutional, Private
5   TOTAL 236,211 405,522 $132,800  


PLANNED BUILDING RENEWAL
Site District Project NASF GSF Cost* Potential
Fund Source
r1 NE Chemical and Nuclear Engineering Bldg Renovation - Phase I 53,009 84,615 $3,900 State
r2 HC Taliaferro/Key Halls Renovation (2nd and 3rd floors) 23,638 39,316 $4,550 Facilities Renewal
2   TOTAL 76,647 123,931 $8,450  


Fall 2001-Fall 2005 Planning Period
Academic Support Facilities
PLANNED NEW CONSTRUCTION
Site District Project NASF GSF Cost* Potential
Fund Source
N6 W Riggs Alumni Center 35,000 60,000 $20,500 Private/Institutional
N7 HC MFRI Headquarters Addition 16,677 20,000 $5,200 State
N8 OP Operations & Maintenance Shops Relocation** 45,146 61,800 $11,100 System
N9 OP Motor Pool Relocation** 6,806 9,300 $1,700 System
N10 OP Campus Mail Facility Relocation** 4,225 5,800 $1,000 System
N11 OP Service Building Relocation** 53,018 72,600 $13,100 System
N12 OP Shuttle UM Relocation** 7,648 10,500 $1,900 System
7   TOTAL 168,520 240,000 $54,500  


PLANNED BUILDING RENEWAL
Site District Project NASF GSF Cost* Potential
Fund Source
R1 E Pocomoke Building Alteration - Public Safety 18,902 24,002 $2,200 System
1   TOTAL 18,902 24,002 $2,200  


Fall 2001-Fall 2005 Planning Period
Auxiliary Enterprise Facilities
PLANNED NEW CONSTRUCTION
Site District Project NASF GSF Cost* Potential
Fund Source
N13 N Softball Stadium 1,600 2,635 $3,900 State
N14 NW Gossett Team House Addition 12,050 18,700 $5,700 Private
N15 HC Health Center Addition/Renovation 29,773 51,900 $14,000 System
N16 SW Mowatt Lane Parking Garage N/A 525,000 $18,200 System
N17 SW Campus Drive Parking Garage - (1,600 spaces) N/A 560,000 $18,700 System
N18 N Comcast Center 289,300 470,000 $126,845 State, Private, System
N19 N Arena Parking Garage N/A 360,000 $16,300 System
7   TOTAL 332,723 1,988,235 $203,645  


PLANNED BUILDING RENEWAL
Site District Project NASF GSF Cost* Potential
Fund Source
R2 W Queen Anne's Hall 21,902 37,237 $7,000 System
R3 HC Fraternity/Sorority Houses (170,171,172) 28,197 32,016 $5,000 System
R4 SW Caroline Hall Renovation 17,955 26,960 $4,900 System
R5 HC Stamp Union Renovation 169,333 256,054 $44,900 System
4   TOTAL 237,387 352,267 $61,800  


Fall 2001-Fall 2005 Planning Period
Public-Private Partnership Facilities
PLANNED NEW CONSTRUCTION
N20 E East Campus Mixed Use Development Phase I - (Includes Conference Center) 896,000 1,280,000 $256,000 PPP
N21 SW Housing/(600 beds) 115,000 145,000 $28,000 PPP
N22 OP New IT Building at College Park Metro site (carrier hotel) 131,400 219,000 $54,800 PPP
N23 NW Day Care Facility 11,000 13,500 $2,500 PPP
N24 N Laboratory for Telecommunications Sciences 51,000 85,000 $25,000 PPP
N25 HC Capstone Housing (799 beds) 186,000 232,532 $44,200 PPP
6   TOTAL 1,390,400 1,975,032 $410,500  


Fall 2001-Fall 2005 Planning Period
Infrastructure Improvements
PLANNED NEW CONSTRUCTION
Site District Project NASF GSF Cost* Potential
Fund Source
I1 NE North Campus SCUB 4,002 13,249 $3,200 State, Institutional
I2 W Lot 1 Boulevard N/A N/A $2,000 State, Institutional, Private
I3 SW Mowatt Lane Improvements and Gateway N/A N/A $1,700 State, Institutional, Private
I4 E/HC Route 1 Pedestrian Median Improvements N/A N/A $1,300 State, Institutional, Private
I5 C Campuswide Pedestrian & Way Finding Improvements - Phase I N/A N/A $1,150 State, Institutional, Private
I6 NW Stadium Drive Gateway Enhancements N/A N/A $1,200 State, Institutional, Private
I7 C Campuswide Bike Improvements - Phase I N/A N/A $700 State, Institutional, Private
I8 C Transporation Improvements to support Shuttle Routes - Phase I N/A N/A $3,100 State, Institutional, Private
8   TOTAL 4,002 13,249 $14,350  


Fall 2001-Fall 2005 Planning Period
Landscape Improvements
PLANNED NEW CONSTRUCTION
Site District Project Cost* Potential
Fund Source
L1 W Campuswide Creek Improvements - Phase I (Terrapin Creek and Pond) $1,700 State, Institutional, Private
L2 N Campuswide Creek Improvements - Phase I (Campus Creek) $1,400 State, Institutional, Private
L3 E Campus Ponds - Phase I (Create Pond East of Rt 1) $700 State, Institutional, Private
L4 HC Campus Drive Pedestrian and Streetscape Improvements $1,700 State, Institutional, Private
L5 N Paint Branch & Stadium Drive Streetscape Improvements $1,070 State, Institutional, Private
L6 SW Campus Malls/Quads - Phase I (North-South Mall in S.W. District - Section I) $2,200 State, Institutional, Private
L7 W President's Lawn Site Improvements $1,000 State, Institutional, Private
L8 SW East-West Pedestrian Connection $4,000 State, Institutional, Private
L9 HC Athletic Fields - Phase I (Engineering Athletic Fields) $1,200 Institutional
9   TOTAL $14,970  


Fall 2001-Fall 2005 Planning Period
Demolitions/Removals
PLANNED DEMOLITIONS/REMOVALS
Building
Number
District Building NASF GSF Reason for Demolition
002 E Harrison Laboratory 56,246 62,004 Site for new facility
003 E Service Building 59,049 83,590 Site for new facility
343 E Campus Mail Facility 4,225 5,380 Site for new facility
011 E Motor Transportation 6,574 8,462 Site for new facility
020 E Motorcycle Storage Bldg 360 416 Site for new facility
006 E Plant Operations & Maintenance Building 15,405 17,466 Site for new facility
012 E Plant Operations & Maintenance Shop 11,832 13,915 Site for new facility
055 E Plant Operations & Maintenance Storage 680 868 Site for new facility
100 E Plant Operations & Maintenance Shop 1,829 2,310 Site for new facility
208 E Temporary Building 666 719 Site for new facility
210 E Plant Operations & Maintenance Storage 499 504 Site for new facility
212 E Plant Operations & Maintenance Shop 1,874 2,088 Site for new facility
215 E Building Services Operations 3,342 4,007 Site for new facility
216 E Heavy Equipment Building 3,267 5,479 Site for new facility
217 E Plant Operations & Maintenance Storage 682 700 Site for new facility
385 E Pest Control Trailer 610 695 Site for new facility
013 E Shuttle Bus Facility 5,862 6,579 Site for new facility
112 E Shuttle Bus Trailer(s) 603 663 Site for new facility
201 E Leonardtown Office Building 10,018 12,748 Site for new facility
204 E Temporary Building (West of 201) 726 868 Site for new facility
207 E Temporary Building (West of 201) 687 719 Site for new facility
238 E Leonardtown Apartment 10,152 11,448 Site for new facility
239 E Leonardtown Apartment 12,582 14,197 Site for new facility
240 E Leonardtown Apartment 10,152 11,448 Site for new facility
241 E Leonardtown Apartment 6,291 7,099 Site for new facility
242 E Leonardtown Apartment 10,152 11,448 Site for new facility
243 E Leonardtown Apartment 5,076 5,724 Site for new facility
041 HC Vending Machine 581 673 Site Development Project
095 NE Garage 2,939 4,090 Site for new facility
106 NE Classroom Building 3,155 5,136 Site Development Project
116 SW Temporary Building (English) 1,347 1,440 Temporary Facility
31   TOTAL 247,463 302,883  


Key
State State Capital Improvement Program (State General Obligation Bonds, USM Academic Revenue Bonds)
System System Funded Construction Program (student/faculty/staff fees)
Institutional Institutional Funds
Facilities Renewal Facilities Renewal Program (projects over $1M)
Private Private fundraising
PPP Public-Private Partnership (private developer financing)
R Renewal of entire facility.
r Partial renewal of the facility.
* Estimated cost is in thousands in January 2002 dollars.
** Facility to be relocated to University property near College Park metro station.
District  
C Campuswide/Various Areas
E East Campus District
HC Historic Core District
N North District
NE Northeast District
NW Northwest District
OP Outlying Properties
SW Southwest District
W West District


Master Plan Home

UM Home | UM Holiday Schedule | UM Directories | UM Search | Weather | Div. of Admin. Affairs | ARES
UM Emergency Preparedness | Dept. of Public Safety | Dept. of Environmental Safety | Dept. of Procurement & Supply
Maintained by University of Maryland Facilities Management