| Campus Construction Project
List ( 262
Projects ) |
||
As of Tuesday, February 09, 2010 |
Current
University Of Maryland Design and Construction Projects |
Facilities Management |
|---|
| STATUS | CAMPUS | TOTAL BUDGET |
DESIGN START |
CONST START |
CONST COMP |
|
| 115 - A.V. Williams Building | ||||||
Design - Pending |
UMCP | A. V. WILLIAMS - 1241/1239 AND 1217/1219 RENOV. EST. | $69,000 |
Feb 2010 |
Jun 2010 |
Aug 2010 |
Construction - Active |
UMCP | A.V.WILLIAMS 1130,1131,1133,1135,1139,1202,1232 FA SYST REPL | $215,000 |
NA |
Dec 2009 |
NA |
Construction - Active |
UMCP | A.V.WILLLIAMS - FM SUPPORT FOR ENERGY PERFORMANCE CONTRACT | $1,100,000 |
NA |
May 2009 |
Oct 2011 |
| 170 - Alpha Delta Pi Sorority (4535 College Ave.) | ||||||
Construction - Subst. Comp. |
UMCP | FRATERNITY/SORORITY HOUSES RENOVATION PH V I I | $15,293,052 |
Aug 2006 |
Nov 2007 |
Feb 2009 |
| 142 - Animal Sciences/Agric. Engrg Bldg | ||||||
Construction - Pending |
UMCP | ANIMAL SCIENCE WET LAB 4148 MODIFICATIONS | $48,157 |
Dec 2009 |
Feb 2010 |
Apr 2010 |
Design - Active |
UMCP | DEDICATED HVAC SYST. FOR RMS 0104, 0108 & 0116 ANIMAL SCI. | $179,679 |
Feb 2010 |
Jun 2010 |
Oct 2010 |
| 145 - Architecture Building | ||||||
Construction - Active |
UMCP | ARCHITECTURE BLDG ELEVATOR CAB ENLARGE | $418,535 |
May 2009 |
Apr 2009 |
Aug 2010 |
Construction - Bidding |
UMCP | ARCHITECTURE BUILDING SKYLIGHT REPLACEMENT | $507,000 |
NA |
Nov 2008 |
NA |
Construction - Active |
UMCP | ARCHITECTURE PIPE LEAK REPAIRS | $100,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | ARCHITECTURE VISUAL DESIGN CENTER OFFICE | $124,283 |
Feb 2009 |
Nov 2009 |
Feb 2010 |
| 146 - Art-Sociology Building | ||||||
Construction - Pending |
UMCP | ART SOCIOLOGY BUILDING SPLINE CEILING AND LIGHT REPLACEMENT | $50,000 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | ART-SOCIOLOGY 4205 & 4213 COLLABORATORY | $369,441 |
Mar 2009 |
Aug 2009 |
Nov 2009 |
Design - Active |
UMCP | FY2010 MD ACCESS - ART SOC LIBRARY 2213 ADA COMPLIANT LIFT | $65,000 |
Nov 2009 |
Mar 2010 |
May 2010 |
| 795 - Avrum Gudelsky Veterinary Center | ||||||
Design - Pending |
UMCP | AVRUM GUDELSKY (795) - MD NEUROIMAGING CENTER. | $1,600,000 |
Feb 2010 |
Aug 2010 |
Mar 2011 |
Construction - Pending |
UMCP | AVRUM GUDELSKY VET. SCIENCE ROOM 1341 DEDICATED EL. LINE INS | $0 |
NA |
Feb 2010 |
Feb 2010 |
Construction - Pending |
UMCP | AVRUM GUDELSKY VET.SCIENCE ROOMS 1412D/E ELECTRIC RENOVATION | $0 |
NA |
Feb 2010 |
Feb 2010 |
Construction - Pending |
UMCP | AVRUM GUDELSKY VETERINARY SCIENCE ROOM1412-D & E RENOVATIONS | $0 |
NA |
Feb 2010 |
NA |
Construction - Active |
UMCP | VET.SCIENCE CENTRIFUGAL CHILLER CONTROL PANELS UPGRADE/REPL. | $35,720 |
NA |
NA |
NA |
| 143 - Benjamin Building | ||||||
Construction - Subst. Comp. |
UMCP | BENJAMIN BUILDING ASBESTOS ABATEMENT | $463,191 |
Jul 2008 |
Nov 2008 |
Jan 2010 |
Construction - Active |
UMCP | BENJAMIN BUILDING CHILLER CONTROL PANEL UPGRADE | $30,000 |
NA |
NA |
NA |
Design - Active |
UMCP | BENJAMIN BUILDING SOUTH LOBBY DESIGN AND CONSTR. OF FINISHES | $115,000 |
Jan 2010 |
May 2010 |
Aug 2010 |
Construction - Active |
UMCP | BENJAMIN BUILLDING CCMS INTEGRATION | $95,146 |
NA |
NA |
NA |
Design - Active |
UMCP | H. BENJAMIN LOBBY(S) (NO.& SO.)UPGRADE AND DESIGN ASSISTANCE | $115,000 |
Jan 2010 |
May 2010 |
Aug 2010 |
| 144 - Biology-Psychology Building | ||||||
Design - Pending |
UMCP | BIO-PSYCH - GRND & 1ST FL REN FOR CCSCMN - NSF GRANT | $1,600,000 |
Mar 2010 |
Dec 2010 |
Jun 2011 |
Design - Active |
UMCP | BIO-PSYCH 4TH FLR HVAC RENOVATION | $3,170,370 |
Oct 2008 |
Apr 2010 |
Jan 2011 |
Construction - Subst. Comp. |
UMCP | BIO-PSYCH BUILDING - SPLINE CEILING REPLACEMENT | $58,000 |
NA |
Dec 2009 |
Jan 2010 |
Construction - Active |
UMCP | BIO-PSYCH ENERGY PERFORMANCE (ESCO) | $7,522,656 |
Sep 2008 |
May 2009 |
NA |
Construction - Active |
UMCP | BIO-PSYCH. - RM 2207 RENOV - SELF DIRECTED PROJECT - D. DALO | $0 |
Jul 2009 |
Jan 2010 |
Mar 2010 |
Construction - Pending |
UMCP | BIO-PSYCHOLOGY #144 - TRACK LIGHTING | $0 |
NA |
Feb 2010 |
Feb 2010 |
Construction - Bidding |
UMCP | BIO-PSYCHOLOGY BUILDING 3124 RENOVATION PLANNING | $151,997 |
Sep 2009 |
Feb 2010 |
Apr 2010 |
| CMP - Campus | ||||||
Construction - Pending |
UMCP | 2002 SENIOR CLASS GIFT PLAQUE INSTALLATION AND PLANTINGS | $15,877 |
Apr 2004 |
Apr 2009 |
NA |
Construction - Active |
UMCP | CAMPUS 2006-2007 SNOW & INCLEMENT WEATHER TASKS | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS 2007-2008 SNOW & INCLEMENT WEATHER RELATED TASKS | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS BOLLARD AND SECURITY GATE INSTALLATION | $30,950 |
Aug 2009 |
Sep 2009 |
Jan 2010 |
Construction - Active |
UMCP | CAMPUS LANDSCAPE UPGRADES | $250,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS TREE REPLACEMENT PROJECT | $80,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS UTILITY MASTER PLAN | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS WIDE STORM WATER DISTRIBUTION | $200,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE EXTERIOR SURFACES CLEANING AND REPAIRS | $300,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FENCING REPLACEMENT/REPAIRS | $50,000 |
NA |
Aug 2009 |
NA |
Construction - Active |
UMCP | CAMPUSWIDE LANDSCAPE IMPROVEMENTS | $278,349 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE PAVING | $200,000 |
NA |
Jul 2009 |
NA |
Construction - Active |
UMCP | CAMPUSWIDE REPAIR/REPLACEMENT OF CURBS, SIDEWALKS & GUTTERS | $200,000 |
NA |
Jul 2009 |
NA |
Construction - Active |
UMCP | CAMPUSWIDE SIGNAGE | $25,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE STORM & SANITARY SEWER REPAIRS | $200,000 |
NA |
NA |
NA |
Design - Active |
UMCP | CHAPEL DRIVE WATER MAIN REPLACEMENT | $172,206 |
Sep 2009 |
Apr 2011 |
Aug 2011 |
Construction - Active |
UMCP | CODE COMPLIANT FIRE ALARM MONITORING SYSTEM - CAMPUS | $1,106,004 |
NA |
NA |
NA |
Design - Active |
UMCP | CSPAC SCUB LINE REPLACEMENT | $1,700,000 |
Sep 2009 |
May 2010 |
Sep 2010 |
Construction - Active |
UMCP | EAST CAMPUS - UTILITY MARKINGS | $135,344 |
Oct 2008 |
May 2009 |
May 2010 |
Design - Active |
UMCP | EAST CAMPUS PHASE I RELOCATION | $590,000 |
Dec 2008 |
Dec 2009 |
Apr 2011 |
Construction - Pending |
UMCP | FEEDER 10 DUCTBANKOF HIGH VOLTAGE DISTRIBUTION SYSTEM SURVEY | $810,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | FM SNOW LOG & INCLEMENT WEATHER RELATED TASKS | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | HOLZAPFEL, MCKELDIN, MENS TOILET ROOMS EVALUATION | $20,500 |
Nov 2009 |
Feb 2010 |
Mar 2010 |
Construction - Active |
UMCP | MASTER SPECS FOR CAMPUS WIDE CONSTRUCTION PROJECTS | $0 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | METZEROTT LAND FILL STORAGE AREA | $141,000 |
NA |
Sep 2009 |
Nov 2009 |
Design - Active |
UMCP | MFRI - NORTHEAST REGIONAL TRAINING CENTER | $9,450,000 |
May 2009 |
May 2010 |
May 2011 |
Construction - Subst. Comp. |
UMCP | MFRI BUILD-OUT OF PRE-ENGINEERED BUILDING | $431,197 |
Dec 2008 |
Jun 2009 |
Oct 2009 |
Design - Active |
UMCP | MOWATT LANE IMPROVEMENTS PHASE I I | $1,000,000 |
Jan 2009 |
Jun 2010 |
Sep 2010 |
Design - Pending |
UMCP | NORTH CAMPUS ELECTRICAL WORK AT LAPLATA, ELLICOTT, ELL.QUAD | $475,000 |
Oct 2009 |
Jan 2010 |
Jan 2010 |
Design - Active |
UMCP | NORTH GATE PARK | $1,995,595 |
Jan 2005 |
May 2010 |
Dec 2010 |
Construction - Active |
UMCP | OIT/NTS DATA & TELEPHONE NETWORK CLOSET REFRESH/REWIRE | $500,000 |
NA |
Apr 2009 |
Jun 2014 |
Construction - Active |
UMCP | RESEARCH PARK CONCRETE POST AND CAMERA CONDUIT INSTALLATION | $8,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | SECURITY WINDOW SCREEN/GRATES - VARIOUS BUILDINGS.. | $40,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | SNOW / INCLEMENT WEATHER TASKS (FY2005) | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | SNOW / INCLEMENT WEATHER TASKS (FY2006) | $0 |
NA |
NA |
NA |
Design - Active |
UMCP | SOUTH CHAPEL LAWN GARDEN OF REMBERANCE DESIGN | $400,000 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | SOUTH WEST DISTRICT SCUB I I PHASE I I PIPING REPLACEMENT | $1,873,240 |
Dec 2008 |
May 2009 |
Sep 2009 |
Design - Active |
UMCP | STORAGE STRUCTURE FOR CRS - N. OF SPH BLDG. | $200,000 |
Sep 2009 |
Mar 2010 |
Jun 2010 |
Construction - Active |
UMCP | TEMPORARY BATTING FACILITY NEXT TO VARSITY TEAM HOUSE ESTIM. | $0 |
NA |
Jan 2010 |
Jan 2010 |
Construction - Active |
UMCP | UM MULTI-HAZARD MITIGATION PLAN COMPLETION | $0 |
NA |
NA |
NA |
| 804 - Center For Educational Partnership (Cep) | ||||||
Construction - Pending |
UMCP | CENTER FOR EDUCATION PARTNERSHIP SEC.MONITOR RECEPT.INSTALL. | $0 |
NA |
Feb 2010 |
Mar 2010 |
Construction - Pending |
UMCP | PROVIDE ELECTRICAL UPGRADES @ CENTER FOR EDUC. PARTNERSHIP | $400,000 |
Jun 2009 |
Mar 2010 |
Apr 2010 |
| 381 - Center For Young Children | ||||||
Construction - Bidding |
UMCP | CENTER FOR YOUNG CHILDREN PLAYGROUND DRAINAGE PROBLEMS | $0 |
NA |
Mar 2010 |
Mar 2010 |
| 090 - Chemical & Nuclear Engineering Building | ||||||
Construction - Subst. Comp. |
UMCP | CHEMICAL & NUCLEAR ENGINEERING HALLWAYS/RESTROOM RENOVATIONS | $300,000 |
Feb 2007 |
Apr 2007 |
Nov 2009 |
| 091 - Chemistry Building | ||||||
Construction - Subst. Comp. |
UMCP | CHEM. BLDG. - IRMS LAB STE - RMS 1212 & 1216 FOR GEOLOGY | $567,182 |
Jan 2009 |
Jun 2009 |
Dec 2009 |
Construction - Active |
UMCP | CHEMISTRY BUILDING PHOENIX LAB COMM. INTERFACE MODBUS REPL. | $11,708 |
NA |
NA |
NA |
Construction - Active |
UMCP | CHEMISTRY WING #1 NORTH ELEVATION LANDSCAPING,BOLLARDS,WALKS | $32,000 |
NA |
NA |
NA |
| 338 - Chesapeake Building | ||||||
Construction - Pending |
UMCP | CHESAPEAKE BUILDING FIRST FLOOR KITCHEN AREA RENOVATIONS | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | CHESAPEAKE BUILDING RM. 4100 CARPET REPLACEMENT ESTIMATE | $58,679 |
NA |
Dec 2009 |
Mar 2010 |
Construction - Pending |
UMCP | CHESAPEAKE BUILDING ROOFTOP SHIPPING CONTAINER OFFICE DESIGN | $0 |
Nov 2009 |
Jan 2010 |
Feb 2010 |
| 386 - Clarice Smith Performing Arts Center At Maryland | ||||||
Construction - Active |
UMCP | CLARICE SMITH PERFORMING ARTS 1908 & 1912 STUDIO RENOV. EST. | $37,000 |
Sep 2009 |
Dec 2009 |
Feb 2010 |
Construction - Pending |
UMCP | CLARICE SMITH PERFORMING ARTS CLASSRM 1809 SPRUNG FLOOR EST | $0 |
NA |
Mar 2010 |
Apr 2010 |
Construction - Pending |
UMCP | PROVIDE ELECTRICAL POWER TO NEWLY INSTALLED SIGN TO RM 2200 | $0 |
NA |
Feb 2010 |
Feb 2010 |
| 162 - Cole Student Activities Building | ||||||
Construction - Pending |
UMCP | COLE #162 - MISCELLANEOUS REPAIRS - BLDG. WIDE | $20,000 |
NA |
Feb 2010 |
Mar 2010 |
Construction - Active |
UMCP | COLE FIELD HOUSE - FM SUPPORT FOR ENERGY PERF. CONTRACT | $1,200,000 |
NA |
Jun 2009 |
May 2010 |
Construction - Active |
UMCP | COLE STUDENT ACTIVITIES DRISKELL CENTER HVAC RENOVATIONS | $8,000 |
NA |
NA |
NA |
| 360 - Comcast Center | ||||||
Construction - Active |
UMCP | COMCAST CENTER EDG RETROFIT | $150,000 |
NA |
NA |
NA |
Construction - Bidding |
UMCP | COMCAST CENTER EXTERIOR STEPS, LANDINGS & RISERS RESURFACING | $100,000 |
NA |
NA |
NA |
| 224 - Computer & Space Sciences Building | ||||||
Construction - Pending |
UMCP | COMPUTER SPACE SCIENCE 2213 DOOR PARTITION REMOVAL | $2,000 |
NA |
NA |
NA |
Design - Active |
UMCP | COMPUTER SPACE SCIENCE B0223/B0259 SUPPLEMENTALOR NEW AHU'S | $99,478 |
Jan 2010 |
May 2010 |
Aug 2010 |
Design - Active |
UMCP | COMPUTER SPACE SCIENCE HIGH PERFORMANCE DATA CENTER | $310,000 |
Mar 2009 |
Oct 2009 |
Jul 2010 |
Construction - Bidding |
UMCP | COMPUTER SPACE SCIENCE JOINT QUANT INST PHASE 2 DESIGN/CONST | $1,201,515 |
Jun 2009 |
Mar 2010 |
Aug 2010 |
Construction - Active |
UMCP | COMPUTER SPACE SCIENCE, 2ND FLOOR WINGS 1/2 JQI RENVOVATIONS | $663,028 |
Oct 2008 |
Aug 2009 |
Feb 2010 |
Construction - Active |
UMCP | COMPUTER SPACE SCIENCES ENERGY PERFORMANCE (ESCO) | $5,520,663 |
Aug 2009 |
NA |
NA |
| 251 - Denton Area Dining Hall | ||||||
Construction - Active |
UMCP | DENTON DINING HALL RENOVATION | $17,800,000 |
Sep 2007 |
Aug 2009 |
Aug 2010 |
| 253 - Easton Hall | ||||||
Design - Active |
UMCP | EASTON HALL A/C INSTALLATION PH 1 | $8,370,000 |
Jun 2009 |
May 2010 |
Aug 2011 |
| 223 - Energy Research Facility | ||||||
Construction - Pending |
UMCP | ENERGY RESEARCH 0102, 0112, 0145 HUMIDITY CONTROL ESTIMATE | $0 |
NA |
NA |
NA |
| 089 - Engineering Laboratory Building | ||||||
Construction - Active |
UMCP | ENGINEERING LAB BUILD.ROOM B0110 SPIRAL STAIR EGRESS DESIGN | $81,286 |
Aug 2009 |
Jan 2010 |
Mar 2010 |
Construction - Active |
UMCP | ENGINEERING LAB ELECTRICAL PANEL/MAIN GEAR REPLACE.PH 2 | $725,000 |
May 2008 |
Sep 2008 |
Jun 2010 |
Design - Active |
UMCP | ENGINEERING LAB IMPROVEMENTS FOR UMERC | $4,300,000 |
Mar 2009 |
Sep 2010 |
Jul 2011 |
| 073 - H.J. Patterson Hall | ||||||
Construction - Active |
UMCP | H. J. PATTERSON - RM. 1206 REN. - SELF DIR. PROJ. - D. DALO | $0 |
Sep 2009 |
Jan 2010 |
Feb 2010 |
Construction - Subst. Comp. |
UMCP | H. J. PATTERSON ASBESTOS ABATEMENT | $23,889 |
NA |
Dec 2008 |
Mar 2009 |
Construction - Active |
UMCP | H. J. PATTERSON NEW RM. 1210 WINDOW HEAT/AC INSTALLATION | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | H. J. PATTERSON PHASE 3 ELECTRICAL UPGRADE | $400,000 |
Sep 2009 |
Oct 2009 |
Apr 2010 |
Construction - Active |
UMCP | H. J. PATTERSON PHASE 4 ELECTRICAL UPGRADE EMERGENCY POWER | $109,000 |
Oct 2009 |
Dec 2009 |
Mar 2010 |
Construction - Bidding |
UMCP | H. J. PATTERSON PHASE II DEMOLITION 3RD FLOOR | $160,000 |
NA |
NA |
NA |
Design - Active |
UMCP | H.J. PATTERSON 3RD FLR WING #2 RENOVATION | $4,884,913 |
Aug 2009 |
Jun 2010 |
Mar 2011 |
Construction - Active |
UMCP | H.J. PATTERSON HALL ROOM 3208 / 3210 FUME HOOD RENOVATIONS | $2,000 |
NA |
Feb 2010 |
Feb 2010 |
| 002 - Harrison Laboratory | ||||||
Construction - Active |
UMCP | HARRISON LAB OLD GREENHOUSES DEMO & REMOVAL SUPPORT | $20,000 |
NA |
NA |
NA |
| 147 - Hornbake Library | ||||||
Construction - Subst. Comp. |
UMCP | HORNBAKE LIBRARY - HUMIDITY CONTROL SYSTEM RENOV. | $2,548,089 |
Sep 2006 |
Nov 2008 |
Jul 2009 |
Construction - Pending |
UMCP | HORNBAKE LIBRARY ESCALATOR WALLS | $25,000 |
NA |
Feb 2010 |
Mar 2010 |
| 083 - J.M. Patterson Building | ||||||
Construction - Active |
UMCP | CHEMICAL & NUC.ENGIN. 2ND FLR STAIR IN-FILL STRUCT. REVIEW | $0 |
Sep 2009 |
Dec 2009 |
Jan 2010 |
Construction - Active |
UMCP | J. M. PATTERSON ROOM 2115 TILE AND MASTIC ABATEMENT | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | J. M. PATTERSON SIGAL LEARNING CENTER INFRASTRUCTURE ASSESS. | $234,971 |
NA |
NA |
NA |
Construction - Pending |
UMCP | J.M. PATTERSON - MOVE ELECTRICAL CONDUIT & LIGHT | $0 |
NA |
Feb 2010 |
Feb 2010 |
| 034 - Jimenez Hall | ||||||
Construction - Active |
UMCP | ESTIMATE - MINOR RENOVATIONS TO ROOMS 1105C, 2106C & 0102 | $3,445 |
NA |
Feb 2010 |
Feb 2010 |
Construction - Active |
UMCP | JIMENEZ HALL 1105 SUITE RENOVATIONS | $0 |
NA |
NA |
NA |
Construction - Pending |
UMCP | PAINTING AND CARPETING OF ADMINISTRATION'S OFFICE | $0 |
NA |
NA |
NA |
| 082 - John S. Toll Physics Building | ||||||
Construction - Pending |
UMCP | FY2010 ACCESS MD - PHYSICS BUILDING 1410 & 1412 ACCESS.IMPR. | $1,500 |
Jun 2009 |
Feb 2010 |
Mar 2010 |
Construction - Active |
UMCP | PHYSICS BLDG - CMTC CONF. RM. EXPANSION | $161,000 |
Aug 2009 |
Nov 2009 |
Feb 2010 |
Construction - Active |
UMCP | PHYSICS BUILD. LECT. HALLS 1410/1412 REVL STAGE MAINT/REPAIR | $22,000 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | PHYSICS BUILDING ASBESTOS ABATEMENT | $298,456 |
Jul 2008 |
Dec 2008 |
Apr 2009 |
Construction - Active |
UMCP | PHYSICS BUILDING LAB 0113 RENOVATIONS ESTIMATE | $8,223 |
NA |
Jan 2010 |
Feb 2010 |
| 059 - Journalism Building | ||||||
Construction - Pending |
UMCP | JOURNALISM BUILDING ASBESTOS REMEDIATION ESTIMATE | $300,000 |
NA |
Feb 2010 |
Mar 2010 |
Design - Active |
UMCP | JOURNALISM BUILDING RENOVATION | $7,135,000 |
Apr 2009 |
Jul 2010 |
Jul 2011 |
| 225 - Kim Engineering Building | ||||||
Construction - Active |
UMCP | KIM ENGINEERING 3RD PARTY INTEGRATION | $23,288 |
NA |
NA |
NA |
Construction - Active |
UMCP | KIM ENGINEERING BUILDING 1ST,2ND,3RD FLOOR HALLWAY PAINTING | $9,324 |
NA |
NA |
NA |
| 417 - Knight Hall | ||||||
Construction - Active |
UMCP | KNIGHT HALL BUILDING | $28,490,000 |
Nov 2006 |
May 2008 |
Nov 2009 |
Construction - Active |
UMCP | KNIGHT HALL-CAPITAL EQUIPMENT. | $1,000,000 |
NA |
NA |
NA |
| 796 - Laboratory For Physical Sciences | ||||||
Design - Active |
UMCP | LAB FOR PHYSICAL SCIENCE LOW VIBRATION ADDITION | $2,917,500 |
Sep 2006 |
Jan 2010 |
Oct 2010 |
Construction - Active |
UMCP | LAB FOR PHYSICAL SCIENCE STORMWATER POND MAINTENANCE | $50,000 |
NA |
NA |
NA |
| 071 - Lee Building | ||||||
Design - Active |
UMCP | LEE BUILDING 2101, 2122, 2122A & 2122B RENOVATIONS ESTIMATE | $415,071 |
Jan 2010 |
May 2010 |
Aug 2010 |
Construction - Active |
UMCP | LEE BUILDING ENERGY PERFORMANCE CONTRACT FM SUPPORT | $800,000 |
NA |
Jun 2009 |
Jun 2010 |
| 077 - Main Administration Building | ||||||
Construction - Subst. Comp. |
UMCP | MAIN ADMIN ELEVATOR | $1,870,000 |
Nov 2007 |
Mar 2009 |
Aug 2009 |
Construction - Active |
UMCP | MAIN ADMINISTRATION BUILDING FIRE ALARM SYSTEM REPLACEMENT | $175,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | MAIN ADMINISTRATION SWITCHGEAR REPLACEMENT | $430,000 |
May 2009 |
Aug 2009 |
Sep 2009 |
| 046 - Marie Mount Hall | ||||||
Design - Active |
UMCP | MARIE MOUNT HALL 2ND FLOOR DESIGN AND RENOVATIONS | $1,000,000 |
Nov 2009 |
May 2010 |
Jul 2010 |
Construction - Active |
UMCP | MARIE MOUNT SCUB CH-1 & CH-2 VFD REPLACEMENT | $175,000 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | RENOVATION - MARIE MOUNT HALL, RMS 3106 & 3108 | $3,000 |
NA |
Jan 2010 |
Feb 2010 |
| 035 - Mckeldin Library | ||||||
Design - Active |
UMCP | MCKELDIN LIBRARY 2100 INFORMATION COMMONS PLANNING & DESIGN | $233,000 |
Jan 2010 |
May 2010 |
Aug 2010 |
Construction - Active |
UMCP | MCKELDIN LIBRARY CCMS INTEGRATION | $6,630 |
NA |
NA |
NA |
Construction - Pending |
UMCP | MCKELDIN LIBRARY WELCOME DESK ELECTRICAL OUTLET INSTALLATION | $0 |
NA |
NA |
NA |
| 199 - Mfri Office/Classroom Building | ||||||
Construction - Active |
UMCP | MFRI BUILDING #199 BAUER COMPRESSOR RELOCATION | $0 |
NA |
Feb 2010 |
Feb 2010 |
| 231 - Microbiology Building | ||||||
Construction - Pending |
UMCP | ESTIMATE WORK UP COST ESTIMATE TO LOWER A PARTITION RM 1109J | $0 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | MICROBIOLOGY BLDG MULTIPLE ROOM RENOVATIONS/REHEAT/DUCTCLEAN | $85,000 |
NA |
Jun 2009 |
Jan 2010 |
Construction - Subst. Comp. |
UMCP | MICROBIOLOGY BLDG.1ST. FLOOR HALLWAY LIGHTING/CEILING RENV. | $50,000 |
NA |
Dec 2009 |
Jan 2010 |
Construction - Pending |
UMCP | MICROBIOLOGY EXTERIOR DORMER/WEATHER BEARING SURFACES EVAL. | $0 |
Feb 2008 |
NA |
NA |
| 052 - Mitchell Building | ||||||
Construction - Active |
UMCP | MITCHELL BUILDING ENERGY PERFORMANCE CONTRACT FM SUPPORT | $800,000 |
NA |
Jun 2009 |
Jun 2010 |
Construction - Subst. Comp. |
UMCP | MITCHELL BUILDING GROUND FLOOR RENOV. - PHASE 1 | $673,133 |
May 2009 |
Sep 2009 |
Jan 2010 |
Construction - Bidding |
UMCP | MITCHELL BUILDING PHASE 2 GROUND FL RENOVATION | $235,655 |
Aug 2009 |
Jan 2010 |
Mar 2010 |
| 404 - Mowatt Lane Parking Garage | ||||||
Construction - Active |
UMCP | MOWATT LANE LICENSE PLATE CAMERA INSTALLATION SUPPORT | $30,500 |
Jan 2010 |
Jan 2101 |
Feb 2010 |
| MLT - Multi Buildings | ||||||
Construction - Active |
UMCP | CAMPUS CLASSROOM CARPET CLEANING BY CONTRACTORS | $5,500 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS ELEVATOR MODERNIZATION, JACK REPL.,REPAIRS OUT.CONTR. | $300,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS MECHANICAL SYSTEM COMPONENT REPLACEMENTS | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS REMEDIATION OF MOLD, MILDEW AND ASBESTOS | $200,000 |
Jul 2009 |
NA |
NA |
Construction - Active |
UMCP | CAMPUS REPAIR/REPLACEMENT OF FUME HOODS AND PUMPS | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS REPLACEMENT OF AGED LOW-TEMP EQUIPMENT AND COMPONENTS | $100,000 |
NA |
NA |
NA |
Design - Active |
UMCP | CAMPUS ROOFTOP FALL PROTECTION OSHA MODIFICATIONS ESTIMATE | $113,492 |
Feb 2010 |
Mar 2010 |
Mar 2010 |
Construction - Active |
UMCP | CAMPUS WIDE INSTALL. OF 25 ELECTRIC, WATER, & BTUH METERS | $9,750 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUS WIDE PIPE INSULATION REPAIRS | $200,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE BUILDING EXTERIOR SURFACE REPAIRS | $529,461 |
NA |
NA |
NA |
Construction - Bidding |
UMCP | CAMPUSWIDE BUILDING WINDOW REPLACEMENT | $100,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE CHAIR REPLACEMENT | $100,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE CLASSROOM PAINTING | $30,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE COMMON AREA PAINTING | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE ELECTRICAL COMPONENT REPAIRS | $300,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE EMERGENCY SHOWER & EYEWASH REPLACEMENT/INSTALL. | $7,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE EXTERIOR DOOR REPAIR/REPLACEMENT | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FAN COIL UNIT REPAIR / REPLACEMENT / UPGRADE | $25,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FIRE ALARM UPGRADES | $65,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FIRE EXTINGUISHERS | $7,500 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FLOOR MAINTENANCE | $75,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE FLOOR MAINTENANCE & REPAIRS | $157,121 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE INTERIOR PLUMBING | $200,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE PAINTING EXTERIOR SURFACES | $250,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE PIPE INSULATION REPAIRS | $200,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE RESTROOM UPGRADES | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | CAMPUSWIDE WINDOW TREATMENT REPLACEMENT | $5,500 |
NA |
NA |
NA |
Construction - Pending |
UMCP | CENTRAL MARYLAND RES. & EDUC. CENTER ASBESTOS REM. ESTIMATE | $60,000 |
NA |
Feb 2010 |
Mar 2010 |
Construction - Active |
UMCP | DENTON HALL RENOVATION | $7,350,000 |
Jan 2009 |
May 2009 |
Aug 2011 |
Construction - Pending |
UMCP | ENERGY RESEARCH FAC. & RECKORD ARMORY ASBESTOS REM. ESTIMATE | $27,924 |
Sep 2009 |
Feb 2010 |
May 2010 |
Construction - Active |
UMCP | FRATERNITY/SORORITY PH 8 RENOVATIONS | $11,530,000 |
Jul 2008 |
Jun 2009 |
Jun 2010 |
Design - Pending |
UMCP | FRATERNITY/SORORITY PH 9 RENOVATIONS | $13,730,000 |
May 2010 |
May 2011 |
May 2012 |
Construction - Active |
UMCP | FY 2009 REPLACEMENT OF AGED FACILITY COMPONENTS & EQUIPTMENT | $400,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | JIMENEZ HALL AND WOODS HALL ASBESTOS REMEDIATION ESTIMATE | $92,108 |
NA |
Feb 2010 |
May 2010 |
Construction - Active |
UMCP | LEE BLDG, COMPUTER SPACE SCIENCE, BIO-PSYCH ACM REMOVAL | $139,340 |
NA |
Dec 2009 |
Mar 2010 |
Construction - Pending |
UMCP | LOWER EASTERN SHORE RES. & EDUC. CENTER ASBESTOS REM. ESTIM. | $96,000 |
NA |
Feb 2010 |
Mar 2010 |
Design - Active |
UMCP | MLT. BUILDINGS - INTERIOR & EXTERIOR LIGHTING UPGRADES | $2,533,834 |
Apr 2005 |
NA |
NA |
Construction - Active |
UMCP | MULTI-BUILDING SYSTEM UPGRADE | $29,636 |
NA |
NA |
NA |
Design - Active |
UMCP | OLD & NEW LEONARDTOWN BALCONY STRUCTURAL REVIEW/ REPAIR RECM | $5,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | PHYSICS,COMPUTER SPACE SC.,MITCHELL,BENJAMIN, FAN COIL REPL. | $75,000 |
NA |
Jan 2010 |
Mar 2010 |
Construction - Active |
UMCP | REPLACEMENT OF AGED HVAC COMPONENT SYSTEMS | $400,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | TYDINGS HALL & MATH BUILDING ASBESTOS REMEDIATION ESTIMATE | $37,407 |
NA |
Feb 2010 |
May 2010 |
Construction - Pending |
UMCP | WYE RESEARCH & EDUCATION CENTER ASBESTOS REM. ESTIMATE | $23,000 |
NA |
Feb 2010 |
Mar 2010 |
Construction - Subst. Comp. |
USM | SHADY GROVE BLDG 2 SMITH SCHOOL OF BUSINESS RENOVATION | $596,232 |
Oct 2008 |
May 2009 |
Sep 2009 |
| 419 - Oakland Hall | ||||||
Construction - Active |
UMCP | OAKLAND HALL RESIDENCE & SCUB | $88,000,000 |
Dec 2008 |
Aug 2009 |
Apr 2011 |
| 805 - Patapsco Building | ||||||
Design - Active |
UMCP | PATAPSCO BUILDING 2ND FLOOR JIFSAN OFFICE FURNITURE SELECT. | $442,000 |
Jan 2010 |
Jul 2010 |
Jul 2010 |
Construction - Subst. Comp. |
UMCP | PATAPSCO BUILDING ROOMS 2119 & 2129 RENOV. DESIGN ADN ESTIM | $442,000 |
Jun 2009 |
Sep 2009 |
Nov 2009 |
| 415 - Physical Sciences Complex | ||||||
Design - Active |
UMCP | PHYSICAL SCIENCES COMPLEX PHASE 1 | $128,681,000 |
Aug 2007 |
Jun 2010 |
Jan 2013 |
| 036 - Plant Sciences Building | ||||||
Design - Active |
UMCP | PLANT SCI BLDG (036) RENOVATION OF 4127 | $25,000 |
Apr 2009 |
Mar 2010 |
Apr 2010 |
Construction - Active |
UMCP | PLANT SCIENCE CH-3 VFD REPLACEMENT | $65,124 |
NA |
NA |
NA |
Construction - Pending |
UMCP | PLANT SCIENCES ROOM 2156 DRAFTING TABLE VYCO COVERING INSTAL | $0 |
NA |
NA |
NA |
| 054 - Preinkert Hall | ||||||
Construction - Pending |
UMCP | ADD AN ADDITIONAL DEDICATED ELECTRICAL OUTLET ROOM 1112R | $0 |
NA |
Feb 2010 |
Feb 2010 |
Construction - Active |
UMCP | FY10 BLDG INTERIOR ARCHITECTURE | $50,000 |
NA |
Dec 2009 |
May 2010 |
| 164 - President'S Residence | ||||||
Design - Active |
UMCP | PRESIDENT'S RESIDENCE PEACE AND FRIENDSHIP SCULPTURE GARDEN | $0 |
Jan 2010 |
Mar 2010 |
Apr 2010 |
| 202 - Regents Drive Parking Garage | ||||||
Construction - Pending |
UMCP | REGENTS DRIVE GARAGE 0200K ELECTRIC HOOKUP FOR PROJ. SCREEN | $0 |
NA |
Feb 2010 |
Feb 2010 |
| 080 - Rossborough Inn | ||||||
Construction - Pending |
UMCP | ROSSBOROUGH INN CARRIAGE HOUISE ELECTRICAL UPGRADE ESTIMATE | $0 |
NA |
NA |
NA |
| 067 - Satellite Central Utilities Building (Scub 2) | ||||||
Design - Active |
UMCP | SCUB 2 PIPING REPLACEMENT PHASE 3 | $970,000 |
Sep 2009 |
May 2010 |
Aug 2010 |
| 416 - Satellite Central Utilities Building (Scub 5) | ||||||
Construction - Active |
UMCP | SCUB 5 - PIPING | $5,022,229 |
Jun 2007 |
May 2009 |
Aug 2010 |
| 255 - School Of Public Health Building | ||||||
Construction - Active |
UMCP | HEALTH & HUMAN PERFORMANCE BLDG. FIRE ALARM REPLACEMENT | $377,227 |
May 2006 |
NA |
May 2009 |
Construction - Pending |
UMCP | SCHOOL OF PUBLIC HEALTH 2360 AND 2362 NEW CARPET/ PAINT ESTM | $0 |
NA |
NA |
NA |
Construction - Active |
UMCP | SCHOOL OF PUBLIC HEALTH BUILDING RENOVATION | $15,000,000 |
Jan 2008 |
Dec 2008 |
Jan 2010 |
Construction - Active |
UMCP | SCHOOL OF PUBLIC HEALTH GPC CEILING TILE REPLACEMENT | $18,468 |
NA |
NA |
NA |
Design - Active |
UMCP | SCHOOL OF PUBLIC HEALTH LECTURE HALL 1312 RENOV. ESTIMATE | $691,590 |
Jan 2010 |
May 2010 |
Aug 2010 |
Construction - Pending |
UMCP | SCHOOL OF PUBLIC HEALTH SUITE 2367 RENOVATIONS ESTIMATE | $0 |
NA |
NA |
NA |
Design - Active |
UMCP | SPH #255 - RENOVATE SUITES 1240 AND 1242 | $420,337 |
Jan 2010 |
Jun 2010 |
Aug 2010 |
| 003 - Service Building | ||||||
Design - Active |
UMCP | EMAIL CONVERSION | $0 |
NA |
NA |
NA |
| 978 - Shady Grove Center Building #1 | ||||||
Construction - Subst. Comp. |
USM | SHADY GROVE BLDG 1 HEALTH CARE SUITE RENOVATION | $733,214 |
Oct 2008 |
May 2009 |
Sep 2009 |
| 037 - Shoemaker Building | ||||||
Construction - Active |
UMCP | SHOEMAKER BUILDING RENOVATIONS | $9,230,000 |
Oct 2007 |
Jun 2009 |
Jun 2010 |
Construction - Active |
UMCP | SHOEMAKER BUILDING RENOVATIONS-FFE | $650,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | SHOEMAKER HALL HV SWITCH & TRANSFORMER RELOCATION | $70,000 |
Oct 2009 |
Oct 2009 |
Nov 2009 |
| 013 - Shuttle Bus Facility | ||||||
Design - A/E Selection |
UMCP | SHUTTLE BUS BUILDING - LOT 4I | $4,329,000 |
NA |
NA |
NA |
| 044 - Skinner Building | ||||||
Construction - Subst. Comp. |
UMCP | FY2010 ACCESS MARYLAND-SKINNER BUILDING MEN'S TOILET 0111 | $15,000 |
Jun 2009 |
Jan 2010 |
Jan 2010 |
| 218 - Stadium Drive Parking Garage | ||||||
Construction - Subst. Comp. |
UMCP | STADIUM DRIVE GARAGE RENOVATION | $1,500,000 |
Feb 2009 |
Jun 2009 |
Aug 2009 |
| 163 - Stamp Student Union | ||||||
Construction - Subst. Comp. |
UMCP | SSU SKYLIGHT AND ROOF REPLACEMENT | $2,759,435 |
May 2007 |
Sep 2008 |
Jun 2009 |
| 141 - Tawes Hall | ||||||
Construction - Subst. Comp. |
UMCP | TAWES HALL CONVERSION | $34,171,716 |
Nov 2005 |
Aug 2007 |
May 2009 |
Construction - Subst. Comp. |
UMCP | TAWES HALL CONVERSION-CAPITAL EQUIPMENT | $2,450,000 |
NA |
NA |
NA |
| 806 - Technology Ventures Building | ||||||
Construction - Pending |
UMCP | 3RD FLOOR REWIRE @ TECHNOLOGY VENTURES BLDG. #806 | $0 |
NA |
Mar 2010 |
Mar 2010 |
| 403 - Terrapin Trail Parking Garage | ||||||
Design - Pending |
UMCP | TERRAPIN DRIVE GARAGE RENOVATION | $1,000,000 |
Jan 2010 |
May 2010 |
Aug 2010 |
| 079 - Turner Hall | ||||||
Construction - Pending |
UMCP | TURNER HALL VISITORS CENTER LOBBY FLAT SCREEN MONIITOR INST. | $1,025 |
NA |
Feb 2010 |
Feb 2010 |
| 042 - Tydings Hall | ||||||
Construction - Active |
UMCP | TYDINGS HALL GR.FLR.VENDING,CLASSRM 1108,2106,OF.3114E,4118D | $10,000 |
NA |
NA |
NA |
| 361 - Tyser Tower | ||||||
Construction - Subst. Comp. |
UMCP | BYRD STADIUM / TYSER TOWER RENOVATION & ADDITION | $50,628,544 |
Nov 2006 |
Dec 2007 |
Aug 2009 |
| 039 - Van Munching Hall | ||||||
Construction - Subst. Comp. |
UMCP | LANDSCAPE MAINTENANCE SHED DESIGN & CONSTRUCTION | $300,000 |
Jan 2009 |
Apr 2009 |
Aug 2009 |
Construction - Active |
UMCP | VAN MUNCHING CCMS UPGRADE | $33,592 |
NA |
NA |
NA |
Construction - Subst. Comp. |
UMCP | VAN MUNCHING HALL ROOM 4568 DESIGN AND RENOVATIONS | $35,000 |
Dec 2009 |
Jan 2010 |
Jan 2010 |
Construction - Active |
UMCP | VAN MUNCHING HALL VALVE REPLACEMENTS | $75,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | VAN MUNCHING HALL WING 1-4 BEAM DET.REPL./WING 5 REALIGNMENT | $26,700 |
NA |
NA |
NA |
Design - Pending |
UMCP | VAN MUNCHING SOUTH ADDITION FOR CAREER SERVICES | $7,000,000 |
Mar 2010 |
Sep 2010 |
May 2011 |
| 047 - Woods Hall | ||||||
Construction - Pending |
UMCP | ADD A NEW SINGLE POLE SWTICHAND REWIRE LIGHTS IN ROOM 0104 | $0 |
NA |
Mar 2010 |
Feb 2010 |
| - | ||||||
Construction - Active |
BSU | BSU-FINE & PERFORMING ARTS | $7,550,000 |
NA |
NA |
NA |
Design - Pending |
BSU | CAMPUSWIDE ELECTRICAL UPGRADES | $3,237,000 |
Jun 2010 |
Aug 2010 |
Jul 2011 |
Construction - Active |
BSU | FINE & PERFORMING ARTS CENTER | $63,469,362 |
Dec 2005 |
Jul 2009 |
Sep 2011 |
Design - Pending |
BSU | NEW STUDENT UNION | $38,720,000 |
Dec 2009 |
Nov 2011 |
Aug 2013 |
Construction - Active |
BSU | REGIONAL STORMWATER FACILITY | $1,363,590 |
NA |
Jul 2009 |
Jan 2010 |
Construction - Active |
CES | CBL/RFO RESEARCH VESSEL FACILITY | $1,375,837 |
Jan 2009 |
Sep 2009 |
Feb 2010 |
Design - Pending |
FSU | COMMUNICATION & INFORMATION TECHNOLOGY CENTER | $58,950,000 |
Jan 2010 |
Nov 2011 |
Nov 2013 |
Construction - Active |
FSU | LANE CENTER RENOVATION & EXPANSION | $17,290,000 |
Jul 2008 |
Sep 2009 |
Dec 2010 |
Design - Active |
SU | MANOKIN HALL RENOVATION | $7,500,000 |
Jun 2009 |
Jan 2010 |
Jul 2010 |
Design - Active |
SU | NANTICOKE HALL RENOVATION | $12,978,040 |
Nov 2009 |
Dec 2010 |
Jul 2011 |
Design - Active |
SU | NOLAND BUILDING RENOVATION | $1,650,000 |
Sep 2009 |
Apr 2010 |
Oct 2010 |
Construction - Subst. Comp. |
SU | PARKING GARAGE | $16,045,000 |
Oct 2007 |
Aug 2008 |
Aug 2009 |
Construction - Active |
SU | PERDUE BUSINESS SCHOOL | $50,553,000 |
Jun 2007 |
Aug 2009 |
Jun 2011 |
Construction - Active |
SU | POCOMOKE RESIDENCE HALL RENOVATION | $7,517,000 |
Sep 2008 |
May 2009 |
Jan 2010 |
Construction - Active |
SU | ST. MARTIN RESIDENCE HALL RENOVATION | $6,548,000 |
Sep 2008 |
May 2009 |
Aug 2009 |
Construction - Subst. Comp. |
SU | TEACHER EDUCATION AND TECH CENTER | $63,568,568 |
Feb 2004 |
Jul 2006 |
Jun 2008 |
Design - Active |
SU | WICOMICO HALL RENOVATION | $7,500,000 |
Sep 2009 |
May 2010 |
Jan 2011 |
Construction - Active |
UMES | SOMERSET HALL / NEW SCHOOL OF PHARMACY RENOVATIONS | $7,191,000 |
Mar 2009 |
Nov 2009 |
Jun 2010 |
Construction - Subst. Comp. |
UMES | SOMERSET HALL ELEVATOR INSTALLATION | $281,500 |
May 2007 |
Apr 2008 |
Feb 2009 |
Construction - Subst. Comp. |
UMES | UTILITY UPGRADE AND SITE IMPROVEMENTS PHASE 3 - CIVIL | $1,664,953 |
Jun 2007 |
Jun 2008 |
Apr 2009 |
Design - Pending |
UMUC | LOT 19 PARKING LOT EXPANSION | $600,000 |
Oct 2009 |
Jul 2010 |
Nov 2010 |
Construction - Subst. Comp. |
USM | SHADY GROVE EDUCATION CENTER 3 | $55,143,021 |
Jan 2002 |
Sep 2005 |
Jul 2007 |
Construction - Subst. Comp. |
USM | SHADY GROVE PARKING GARAGE | $12,525,000 |
Nov 2007 |
Jun 2008 |
Jul 2009 |
Total: 262 |
Projects |
$993,441,493 |
||||
|---|---|---|---|---|---|---|